A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget.If the cumulative actual cost is greater than the cumulative earned value, then
A) the FCAC is greater than the TBC.
B) the FCAC is less than the TBC.
C) the FCAC cannot be calculated with the values given.
D) additional information is needed to predict the FCAC.
Correct Answer:
Verified
Q52: Another indicator of cost performance is cost
Q53: The _ is the amount that was
Q54: As data are collected on _, including
Q55: The _ is the product of the
Q56: The cost performance index (CPI)is a measure
Q58: Calculate the forecasted cost at completion if
Q59: Plot _ curves on the same graph
Q60: Determining the earned value involves collecting data
Q61: Calculate the forecasted cost at completion if
Q62: Allocating total project costs for the various
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents