As Data Are Collected on ____, Including Portions of Any

Question 54

Multiple Choice

As data are collected on ____, including portions of any committed cost, they need to be totaled by work package so that they can be compared to the ____


A) planned cost, total budgeted cost.
B) budgeted cost of work scheduled, actual cost of work performed.
C) actual cost, cumulative budgeted cost.
D) cumulative earned value, total budgeted cost.