A third method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost.If the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then
A) the FCAC is greater than the TBC.
B) the FCAC is less than the TBC.
C) the FCAC cannot be calculated with the values given.
D) additional information is needed to predict the FCAC.
Correct Answer:
Verified
Q46: Calculate the forecasted cost at completion if
Q47: Costs are _ when an item is
Q48: The _ is the amount that was
Q49: It's important that the person estimating the
Q50: Calculate the cost variance if the cumulative
Q52: Another indicator of cost performance is cost
Q53: The _ is the amount that was
Q54: As data are collected on _, including
Q55: The _ is the product of the
Q56: The cost performance index (CPI)is a measure
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents