The actual cost on a project is
A) the planned amount to be spent on the project plus unexpected costs
B) the sum of the budgeted costs.
C) the amount of funds expended on the project.
D) the total of the unexpected costs.
Correct Answer:
Verified
Q87: The cumulative earned value of the project
Q88: The cumulative actual costs of a project
Q89: The forecasted cost at completion is
A) a
Q90: The key to managing a cash flow
Q91: The cumulative budgeted cost is
A) the aggregate
Q93: If the project has a negative cost
Q94: The positive cost variance means
A) more money
Q95: For a project, the TBC = $200,000,
Q96: The key to managing _ is to
Q97: A cost performance index greater than 1.0
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents