The cumulative earned value of the project is
A) the sum of the planned costs of the project
B) the sum of the budgeted costs of the work actually performed.
C) the sum of the budgeted cost of the work scheduled.
D) the sum of the differences between what was planned and the actual costs.
Correct Answer:
Verified
Q82: The total budgeted cost for the project
Q83: The key to effective cost control is
Q84: The estimated cost of an activity should
Q85: The two-step process for budgeting is
A) estimate
Q86: The earned value is
A) the budgeted cost
Q88: The cumulative actual costs of a project
Q89: The forecasted cost at completion is
A) a
Q90: The key to managing a cash flow
Q91: The cumulative budgeted cost is
A) the aggregate
Q92: The actual cost on a project is
A)