The earned value is
A) the budgeted cost of the work scheduled.
B) the sum of the actual costs of the project.
C) difference between what was planned and the actual costs.
D) the budgeted costs of the work actually performed.
Correct Answer:
Verified
Q81: The to-complete performance index is
A) the amount
Q82: The total budgeted cost for the project
Q83: The key to effective cost control is
Q84: The estimated cost of an activity should
Q85: The two-step process for budgeting is
A) estimate
Q87: The cumulative earned value of the project
Q88: The cumulative actual costs of a project
Q89: The forecasted cost at completion is
A) a
Q90: The key to managing a cash flow
Q91: The cumulative budgeted cost is
A) the aggregate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents