With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible to use three time estimates:
A) an original estimate, a petrified estimate, and a most likely estimate.
B) an optimistic estimate, a pessimistic estimate, and a most likely estimate.
C) an optimized estimate, a primary estimate, and a most likely estimate.
D) an opportunity estimate, a pragmatic estimate, and a most likely estimate.
Correct Answer:
Verified
Q48: Latest start time is calculated by
A) subtracting
Q49: Total Slack is sometimes called
A) drift.
B) ride.
C)
Q50: Calculate the earliest start for Task D
Q51: Calculate the latest start for Task D
Q52: Latest start time (LS)is the latest time
Q54: Earliest finish time (EF)is the earliest time
Q55: Calculate the latest finish for Task B
Q56: Total slack for the project is the
Q57: Calculate the earliest start for Task B
Q58: Calculate the latest start for Task B
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents