Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.
A) day 6
B) day 3
C) day 4
D) Cannot be calculated based upon information given.