The earliest start time for a specific activity must be ____ the latest of all the earliest finish times of all the activities leading directly into that specific activity.
A) earlier than
B) the same as
C) the same as or later than
D) later than
Correct Answer:
Verified
Q41: In order to establish a basis from
Q42: Throughout the performance of the project, some
Q43: Calculate the latest finish for Task D
Q44: The ES and EF times are determined
Q45: Calculate the earliest finish for Task D
Q47: Latest finish time (LF)is the latest time
Q48: Latest start time is calculated by
A) subtracting
Q49: Total Slack is sometimes called
A) drift.
B) ride.
C)
Q50: Calculate the earliest start for Task D
Q51: Calculate the latest start for Task D