Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
A) day 9
B) day 10
C) day 12
D) Cannot be calculated based upon information given.
Correct Answer:
Verified
Q38: People sometimes perform to expectations, their effort
Q39: Project management is a proactive approach to
Q40: When estimating resources for activities to estimate
Q41: In order to establish a basis from
Q42: Throughout the performance of the project, some
Q44: The ES and EF times are determined
Q45: Calculate the earliest finish for Task D
Q46: The earliest start time for a specific
Q47: Latest finish time (LF)is the latest time
Q48: Latest start time is calculated by
A) subtracting
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents