An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the variance of the activity?
A) 4.17
B) 25.17
C) 17.36
D) 10.33
Correct Answer:
Verified
Q24: The variance of an activity is given
Q42: An activity has a pessimistic time that
Q43: Ray's shipment of materials hit every red
Q44: The length of time expected to complete
Q45: What is the late start time for
Q47: Based on the activity network pictured,what is
Q48: An activity has an optimistic time estimate
Q49: What is the early start time for
Q50: Network logic suggests that: Q51: An activity has an optimistic time estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents