Question 41
Multiple Choice
The variance of an activity is given by:
Question 42
Multiple Choice
An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time.If the activity variance is 10,what is the expected time?
Question 43
Multiple Choice
Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:
Question 44
Multiple Choice
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
Question 45
Multiple Choice
What is the late start time for Activity E given the activity times and precedence requirements shown in the table?
Question 46
Multiple Choice
An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the variance of the activity?
Question 47
Multiple Choice
Based on the activity network pictured,what is the best statement?
Question 48
Multiple Choice
An activity has an optimistic time estimate of 7 days,a most likely estimate of 12 days,and a pessimistic estimate of 20 days.What is the expected duration of the activity?
Question 49
Multiple Choice
What is the early start time for Activity D given the activity times and precedence requirements shown in the table?
Question 50
Multiple Choice
Network logic suggests that:
Question 51
Multiple Choice
An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the expected duration of the activity?
Question 52
Multiple Choice
Which of these statements about this network is best?
Question 53
Multiple Choice
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?
Question 54
Multiple Choice
Based on the activity network pictured,what is the best statement?
Question 55
Multiple Choice
What is the late start time for Activity B given the activity times and precedence requirements shown in the table?
Question 56
Multiple Choice
What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?
Question 57
Multiple Choice
An activity has an optimistic time estimate of 7 days,a most likely estimate of 12 days,and a pessimistic estimate of 20 days.What is the expected standard deviation of the activity?