Activity Z has estimates a = 5,b = 10,m = 7;activity X has estimates a = 4,b = 11,m = 6;and activity Y has estimates a = 3,b = 12,m = 8.Which of the following statements is best?
A) Activity X is longer than Activity Y.
B) Activity X has a higher standard deviation than Activity Z.
C) Activity Z is shorter than Activity Y.
D) Activity Y has a smaller variance than Activity Z.
Correct Answer:
Verified
Q53: What is the late finish time for
Q54: Based on the activity network pictured,what is
Q55: What is the late start time for
Q56: What is the earliest that Activity D
Q57: An activity has an optimistic time estimate
Q59: What is the early start time for
Q60: What is the early finish time for
Q61: Project Test Bank is composed of activities
Q62: Use the network diagram and activity lengths
Q63: Use the network diagram and activity lengths
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents