Use the information in the table to determine the early start time for Activity B.
A) day 10
B) day 8
C) day 9
D) day 11
Correct Answer:
Verified
Q48: An activity has an optimistic time estimate
Q50: What is the early start time for
Q51: What is the slack time for activity
Q53: Use the network diagram and activity lengths
Q54: What is the early finish time for
Q56: What is the slack time for Activity
Q57: An activity has an optimistic time estimate
Q57: What is the float start time for
Q58: What is the early start time for
Q60: What is the slack time for Activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents