Quiz 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Question 41
Multiple Choice
What is the late start time for Activity B given the activity times and precedence requirements shown in the table?
Question 42
Multiple Choice
Use the information in the table to determine the slack time for Activity B.
Question 43
Multiple Choice
What is the late start time for Activity E given the activity times and precedence requirements shown in the table?
Question 44
Multiple Choice
Activity Z has estimates a=5, b=10, m=7; activity X has estimates a=4, b=11, m=6; and activity Y has estimates a=3, b=12, m=8. Which of the following statements is best?
Question 45
Multiple Choice
Use the information in the table to determine the late start time for Activity E.
Question 46
Multiple Choice
Use the information in the table to determine the early finish time for Activity D.
Question 47
Multiple Choice
An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time. If the activity variance is 10, what is the expected time?
Question 48
Multiple Choice
Use the information in the table to determine the late finish time for Activity B.
Question 49
Multiple Choice
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?
Question 50
Multiple Choice
What is the early start time for Activity G given the activity times and precedence requirements shown in the table?
Question 51
Multiple Choice
What is the slack time for activity E?
Question 52
Multiple Choice
An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected standard deviation of the activity?
Question 53
Multiple Choice
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.
Question 54
Multiple Choice
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?
Question 55
Multiple Choice
Use the information in the table to determine the early start time for Activity B.
Question 56
Multiple Choice
What is the slack time for Activity B given the activity times and precedence requirements shown in the table?
Question 57
Multiple Choice
What is the float start time for Activity C given the activity times and precedence requirements shown in the table?
Question 58
Multiple Choice
What is the early start time for Activity D given the activity times and precedence requirements shown in the table?
Question 59
Multiple Choice
An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected duration of the activity?