Quiz 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Question 1
Short Answer
The longest route through the network is the __________.
Question 2
Short Answer
__________ activities have two or more immediate predecessors.
Question 3
Short Answer
Because an activity's pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate, the __________ better represents the distribution of possible alternative durations.
Question 4
True/False
A merge activity has two or more immediate predecessors.
Question 5
Short Answer
There is no slack on the project __________.
Question 6
True/False
Float is always measured in exactly the same way as slack.
Question 7
Short Answer
Activities that can be worked on simultaneously are __________ activities.
Question 8
True/False
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.