Question 21
Multiple Choice
An activity has an optimistic time estimate of 15 days, a most likely estimate of 24 days, and a pessimistic estimate of 40 days. What is the variance of the activity?
Question 22
Multiple Choice
Which of these statements about this network is best?
Question 23
Multiple Choice
An activity with two or more immediate predecessors is a(n) :
Question 24
Multiple Choice
The term ordered activity means:
Question 25
Multiple Choice
The variance of an activity is given by:
Question 26
Multiple Choice
An activity has an optimistic time estimate of 15 days, a most likely estimate of 24 days, and a pessimistic estimate of 40 days. What is the expected duration of the activity?