All of the following problems contribute to difficulty in estimating activity durations accurately EXCEPT:
A) merging - the case of multiple predecessors
B) omissions - leaving out key activities
C) general uncertainty in the estimate
D) fixed price estimates for work packages to be outsourced
Correct Answer:
Verified
Q21: Q30: The sequencing of activities is often based Q31: Which of the following remedies may reduce Q32: The total number of work periods (not Q32: Which of the following responses identifies a Q33: Q34: A scheduled activity that determines when a Q36: Creating a realistic schedule is often an Q37: All of the following items can provide Q37: Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents