Solved

All of the Following Problems Contribute to Difficulty in Estimating

Question 33

Multiple Choice

All of the following problems contribute to difficulty in estimating activity durations accurately EXCEPT:


A) merging - the case of multiple predecessors
B) omissions - leaving out key activities
C) general uncertainty in the estimate
D) fixed price estimates for work packages to be outsourced

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents