The sequencing of activities is often based upon dependencies between the activities. The dependencies that should guide activity sequencing can be either:
A) mandatory or discretionary
B) arbitrary or capricious
C) logical or illogical
D) interior or exterior
Correct Answer:
Verified
Q21: Q25: All of the following strategies can help Q26: The total amount of time a schedule Q27: Faced with significant schedule challenges,the project manager Q31: Which of the following remedies may reduce Q32: The total number of work periods (not Q32: Which of the following responses identifies a