Multiple Choice
The total amount of time a schedule activity may be delayed from its early start date without delaying the project finish date is known as:
A) reserve
B) total float
C) contingency
D) lead
Correct Answer:
Verified
Related Questions
Q21: Q24: Milestones are important points in a project Q25: All of the following strategies can help Q27: Faced with significant schedule challenges,the project manager Q30: The sequencing of activities is often based Q31: Q31: Which of the following remedies may reduce Q33: Estimating the number of work periods that Q33: Q35: Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents