When using a control chart,a point that occurs above the upper control limit typically means the variation is enough that it is not likely to have happened purely by chance - rather some sort of special cause explains the variation.
Correct Answer:
Verified
Q2: The purpose of quality control on projects
Q3: During project execution,monitoring refers to the act
Q4: When using earned value techniques,Actual Cost (AC)refers
Q6: The concept behind a balanced scorecard is
Q7: The Cost Variance (CV)is a measure of
Q8: When project managers authorize project work,they should
Q9: The Schedule Performance Index (SPI)is a measure
Q10: Earned Value (EV)is the authorized budget assigned
Q13: Inspection is keeping errors out of process
Q15: Two types of control are used extensively