All of the following accurately describe earned value management EXCEPT:
A) It is used to objectively measure project performance and progress.
B) It enables a project team to understand progress in terms of both cost and schedule.
C) It is good for performance reporting but not for forecasting
D) It is in essence a decision-making tool.
Correct Answer:
Verified
Q23: One useful method of process improvement involves
Q28: Q30: Q33: Q33: Which of the following are appropriate lessons Q37: When a project manager asks clarifying questions Q38: While the project is underway,effective information distribution Q40: All of the following accurately apply to Q42: Identify a business process that is often Q43: Describe how you would adopt a balanced Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents