Based on the activity network pictured,what is the best statement? 
A) Activity C is a burst activity.
B) Activity E has one predecessor,Activity B.
C) Activity A and Activity C are merge activities.
D) There are no serial activities in this network.
Correct Answer:
Verified
Q49: What is the early start time for
Q50: Network logic suggests that: Q51: An activity has an optimistic time estimate Q52: Which of these statements about this network Q53: What is the late finish time for Q55: What is the late start time for Q56: What is the earliest that Activity D Q57: An activity has an optimistic time estimate Q58: Activity Z has estimates a = 5,b Q59: What is the early start time for![]()