Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?
A) week 6
B) week 2
C) week 4
D) week 3
Correct Answer:
Verified