A Project Consisting of Six Activities Is Shown in the Table.If

Question 43

Multiple Choice

A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements? A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements?   A) day 21 B) day 18 C) day 24 D) day 15


A) day 21
B) day 18
C) day 24
D) day 15

Correct Answer:

verifed

Verified