Exhibit 18-1 In 2010, Alpha Construction began work on a contract with a price of $850, 000 and estimated costs of $595, 000.Data for each year of the contract are as follows:
201020112012 Costs incurred chring the year $238,000$319,600$105,000 Estimated costs to complete 357,000139,4000 Partial billings 260,000210,000380,000 Collections 240,000200,000410,000\begin{array}{llll}&2010&2011&2012\\\text { Costs incurred chring the year } & \$ 238,000 & \$ 319,600 & \$ 105,000 \\\text { Estimated costs to complete } & 357,000 & 139,400 & -0- \\\text { Partial billings } & 260,000 & 210,000 & 380,000 \\\text { Collections } & 240,000 & 200,000 & 410,000\end{array}


-Refer to Exhibit 18-1.Under the percentage-of-completion method of revenue recognition, the net amount reported for construction in progress inventory at the end of 2011 would be


A) $ 87, 600
B) $189, 600
C) $210, 000
D) $312, 000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents