Exhibit 18-2 The following information relates to a project of the Sarasota Construction Company:
201020112012 Construction costs incurred $136,000$546,500$200,000 Estimated costs to complete 714,000227,500\begin{array}{llll}&2010&2011&2012\\\text { Construction costs incurred } & \$ 136,000 & \$ 546,500 & \$ 200,000 \\\text { Estimated costs to complete } & 714,000 & 227,500 & --\end{array}

The contract price was $1, 000, 000.Sarasota used the percentage-of-completion method of revenue recognition.
-
Refer to Exhibit 18-2.What amount of gross profit was recognized in 2012?


A) $ 29, 375
B) $ 50, 000
C) $117, 500
D) $150, 000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents