What is the difference between a Gantt chart and a PERT chart?
Gantt charts are used for planning service activities, while PERT charts are used for planning production activities.
PERT charts show the critical path for meeting project goals, but Gantt charts do not.
Gantt charts focus more on efficiency, while PERT charts focus more on effectiveness.
PERT charts were formerly used more widely than Gantt charts, but the reverse is now true.
There actually is no difference between Gantt charts and PERT charts; they are both used to schedule activities.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q70: The major objective of JIT is to
minimize
Q71: What is the meaning of "operations control"?
Planning
Q72: A _ diagrams steps to be performed
Q73: What advantages are obtained from the use
Q74: John's job responsibilities include the acquisition of
Q76: The management of the production process designed
Q77: Mount Sinai Hospital no longer keeps any
Q78: Tom is concerned with the storage of
Q79: Once plans identify needed resources and how
Q80: Betty is a production supervisor in a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents