For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:
-Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D.
A) w = 2, x = 6
B) w = 4, x = 8
C) w = 5, x = 9
D) w = 6, x = 10
E) None of the above
Correct Answer: