The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
-The plumber has scheduled another small job at 6:00 p.m. If it takes 1/2 hour to drive from the Spalding's to the other job, what is the probability the plumber will be able to make the 6:00 p.m. appointment on time?
A) 63%
B) 75%
C) 89%
D) 95%
E) 99%
Correct Answer:
Verified
Q11: Which of the following is an example
Q12: The following network is the basis for
Q13: For the next two questions, refer to
Q14: Which of the following is NOT a
Q15: The following network is the basis for
Q16: The following information is the basis
Q18: For the next two questions, refer to
Q19: The following software development plan is the
Q20: The table below shows PERT estimates
Q21: The following software development plan is the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents