Given the following information at week 12 of a 54-week project:
PV = 1,200 hours
EV = 1,400 hours
AC = 1,000 hours
Schedule variance percent SV%) and cost variance percent CV%) , respectively, would be:
A) -14.29%, -33.33%
B) +14.29%, +33.33%
C) +16.67%, +28.57%
D) -16.67%, -28.57%
E) None of these, the answer is: ________________ show your work)
Correct Answer:
Verified
Q1: Given the following information about a project:
EV
Q2: Given the following information about a project
Q3: Given the following information about a project:
EV
Q5: Given the following information at week 19
Q6: Which of the following is/are sources of
Q7: What is the difference between planned value
Q8: Which of the following offers the best
Q9: A project task is scheduled to begin
Q10: A project team has worked for six
Q11: Which of the following project monitoring tools
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents