Given the following information about a project:
EV = $1,000,000
PV = $2,000,000
AC = $3,000,000
BAC = $4,000,000
What can we legitimately say about this project if this is the only information we have?


A) 25% of the total work planned has been completed.
B) The project is ahead of schedule.
C) The project is under budget.
D) It is highly likely the project will be completed on time.
E) The CPI is .33.
F) A and E only