Question 61
Multiple Choice
What assumption about the behaviour of total costs occurs within the relevant range of activity?
Question 62
Multiple Choice
Which one of the following would be the same total amount on a flexible budget and a static budget if the activity level is different for the two types of budgets?
Question 63
Multiple Choice
Use the following information to answer questions EKPN Company prepared the following data in its static budget based on 150,000 machine hours:
Direct Materials
$
450
,
000
Direct Labour
225
,
000
Variable Overhead
1
,
125
,
000
Fixed Overhead
2
,
100
,
000
Actual Results:
Machine Hours
Direct Materials
$
60
,
000
hours
Direct Labour
$
475
,
000
Variable Overhead
245
,
000
Fixed Overhead
1
,
150
,
000
2
,
110
,
000
\begin{array}{lr}\text { Direct Materials } & \$ 450,000 \\\text { Direct Labour } & 225,000 \\\text { Variable Overhead } & 1,125,000 \\\text { Fixed Overhead } & 2,100,000\\\\\text { Actual Results: } \\\text { Machine Hours } & \\\text { Direct Materials } & \$ 60,000 \text { hours } \\\text { Direct Labour } & \$ 475,000 \\\text { Variable Overhead } & 245,000 \\\text { Fixed Overhead } & 1,150,000 \\& 2,110,000\end{array}
Direct Materials
Direct Labour
Variable Overhead
Fixed Overhead
Actual Results:
Machine Hours
Direct Materials
Direct Labour
Variable Overhead
Fixed Overhead
$450
,
000
225
,
000
1
,
125
,
000
2
,
100
,
000
$60
,
000
hours
$475
,
000
245
,
000
1
,
150
,
000
2
,
110
,
000
-What possible reason could explain the difference between the actual fixed overhead costs and the budgeted fixed overhead costs?
Question 64
Multiple Choice
Use the following information to answer questions EKPN Company prepared the following data in its static budget based on 150,000 machine hours:
Direct Materials
$
450
,
000
Direct Labour
225
,
000
Variable Overhead
1
,
125
,
000
Fixed Overhead
2
,
100
,
000
Actual Results:
Machine Hours
Direct Materials
$
60
,
000
hours
Direct Labour
$
475
,
000
Variable Overhead
245
,
000
Fixed Overhead
1
,
150
,
000
2
,
110
,
000
\begin{array}{lr}\text { Direct Materials } & \$ 450,000 \\\text { Direct Labour } & 225,000 \\\text { Variable Overhead } & 1,125,000 \\\text { Fixed Overhead } & 2,100,000\\\\\text { Actual Results: } \\\text { Machine Hours } & \\\text { Direct Materials } & \$ 60,000 \text { hours } \\\text { Direct Labour } & \$ 475,000 \\\text { Variable Overhead } & 245,000 \\\text { Fixed Overhead } & 1,150,000 \\& 2,110,000\end{array}
Direct Materials
Direct Labour
Variable Overhead
Fixed Overhead
Actual Results:
Machine Hours
Direct Materials
Direct Labour
Variable Overhead
Fixed Overhead
$450
,
000
225
,
000
1
,
125
,
000
2
,
100
,
000
$60
,
000
hours
$475
,
000
245
,
000
1
,
150
,
000
2
,
110
,
000
-What was the budgeted variable costs per machine hour for variable overhead, rounded to the nearest whole cent?
Question 65
Multiple Choice
Nextel Communications uses management by exception.Which differences between planned and actual results will it investigate?
Question 66
Multiple Choice
What is the primary difference between a static budget and a flexible budget?
Question 67
Multiple Choice
Which statement is true about the activity index used in preparing the flexible budget?
Question 68
Multiple Choice
Which one of the following statements is true concerning a flexible budget?
Question 69
Multiple Choice
How does a graph of a flexible budget compare to a CVP graph?
Question 70
Multiple Choice
Use the following information to answer questions EKPN Company prepared the following data in its static budget based on 150,000 machine hours:
Direct Materials
$
450
,
000
Direct Labour
225
,
000
Variable Overhead
1
,
125
,
000
Fixed Overhead
2
,
100
,
000
Actual Results:
Machine Hours
Direct Materials
$
60
,
000
hours
Direct Labour
$
475
,
000
Variable Overhead
245
,
000
Fixed Overhead
1
,
150
,
000
2
,
110
,
000
\begin{array}{lr}\text { Direct Materials } & \$ 450,000 \\\text { Direct Labour } & 225,000 \\\text { Variable Overhead } & 1,125,000 \\\text { Fixed Overhead } & 2,100,000\\\\\text { Actual Results: } \\\text { Machine Hours } & \\\text { Direct Materials } & \$ 60,000 \text { hours } \\\text { Direct Labour } & \$ 475,000 \\\text { Variable Overhead } & 245,000 \\\text { Fixed Overhead } & 1,150,000 \\& 2,110,000\end{array}
Direct Materials
Direct Labour
Variable Overhead
Fixed Overhead
Actual Results:
Machine Hours
Direct Materials
Direct Labour
Variable Overhead
Fixed Overhead
$450
,
000
225
,
000
1
,
125
,
000
2
,
100
,
000
$60
,
000
hours
$475
,
000
245
,
000
1
,
150
,
000
2
,
110
,
000
-What is the budgeted Direct Labour cost at the actual level of activity?
Question 71
Multiple Choice
Surf N Waves planned to sell 27,000 surfboards, however the actual number sold totalled 23,000.Which one of the following provides the best comparison of the cost data associated with the sales?