What Is a Work Breakdown Structure

Question 50

Multiple Choice

What is a work breakdown structure?


A) A list of the activities making up the higher levels of the project
B) A definition of the hierarchy of project tasks, subtasks, and work packages
C) A depiction of the activities making up a project
D) A Gantt chart
E) A structure that is incompatible with the Critical Path Method

Correct Answer: