For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10.Which of the following statements is ?
A) The Late Finish is 12
B) The Early Finish is 10
C) The slack for this activity is 2
D) The duration of this activity is 2
E) The activity is on the critical path
Correct Answer:
Verified