Which one of the following best describes the critical path of a PERT/CPM network?
A) the sequence of activities between a project's start and finish that takes the longest time to complete
B) the sequence of activities between a project's start and finish that has the maximum amount of activity slack
C) the set of activities that has no precedence relationships
D) the sequence of activities that has the lowest normal activity cost
Correct Answer:
Verified
Q16: What characteristics should be considered when selecting
Q17: A(n) _ is an interrelated set of
Q18: Activity times for a project are estimated
Q19: The project's objective statement should contain:
A) slack
Q20: The _ is a statement of all
Q22: Figure to accompany Table 7.1
Q23: To obtain the latest start and latest
Q24: Figure to accompany Table 7.1
Q25: Figure 7.2 Q26: Figure 7.1
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents