Figure 7.2
-Which one of the following conditions violates the assumptions of PERT/CPM networks?
A) Some activities can have zero variance.
B) Costs increase linearly as activity time is reduced below its normal time.
C) Two activities tied together by an arc are overlapping and can be worked on simultaneously.
D) There can be more than one critical path in a network.
Correct Answer:
Verified
Q20: The _ is a statement of all
Q21: Which one of the following best describes
Q22: Figure to accompany Table 7.1
Q23: To obtain the latest start and latest
Q24: Figure to accompany Table 7.1
Q26: Figure 7.1 Q27: Figure to accompany Table 7.1 Q28: A critical path is any sequence of Q29: A Gantt chart is a project schedule Q30: Figure 7.2