Figure 7.2
-Which one of the following statements regarding Figure 7.2 is True?
A) Activity S cannot finish until activity T finishes.
B) Activity T cannot begin until activity U is completed.
C) Activity U cannot begin until activities S and T have been completed.
D) Activity V cannot begin until activity S has been completed.
Correct Answer:
Verified
Q25: Figure 7.2 Q26: Figure 7.1 Q27: Figure to accompany Table 7.1 Q28: A critical path is any sequence of Q29: A Gantt chart is a project schedule Q31: The _ is the sequence of activities Q32: The earliest start time for an activity Q33: The earliest start time is never the Q34: A project has three paths. A-B-C has Q35: Activity slack is defined as: