Table 7.5 -Using Table 7.5, How Many Days Can Activity C Be

Question 52

Multiple Choice
Table 7.5
 
-Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time?
A) 0 days 
B) 2 days 
C) 5 days 
D) 7 days

Table 7.5
Table 7.5    -Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time? A)  0 days B)  2 days C)  5 days D)  7 days
-Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time?


A) 0 days
B) 2 days
C) 5 days
D) 7 days

Correct Answer: