Multiple Choice

Table 7.6
-Using Table 7.6, suppose activity D can be shortened from four days to one day. Assume all other activity times remain the same. How much shorter will the total project earliest completion time become?
A) zero days
B) one day
C) two days
D) three days
Correct Answer:
Verified
Related Questions
Q57: Table 7.4 Q58: Table 7.5 Q59: Table 7.5 Q60: Table 7.4 Q61: Figure to accompany Table 7.7 Q63: Figure to accompany Table 7.7 Q64: Figure to accompany Table 7.7 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents