Multiple Choice

Table 7.5
-Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using Table 7.5, how much longer will the project last than initially estimated?
A) 15 days
B) 0 days
C) 7 days
D) 3 days
Correct Answer:
Verified