Table 7.6 -Using Table 7.6, Suppose Activity I Is Delayed, Taking Eight

Question 77

Multiple Choice
Table 7.6
 
-Using Table 7.6, suppose activity I is delayed, taking eight days to complete instead of two days. Assume all other activity times remain the same. How much longer will the total project earliest completion time become?
A) zero days 
B) one or two days 
C) three or four days 
D) five or six days

Table 7.6
Table 7.6    -Using Table 7.6, suppose activity I is delayed, taking eight days to complete instead of two days. Assume all other activity times remain the same. How much longer will the total project earliest completion time become? A)  zero days B)  one or two days C)  three or four days D)  five or six days
-Using Table 7.6, suppose activity I is delayed, taking eight days to complete instead of two days. Assume all other activity times remain the same. How much longer will the total project earliest completion time become?


A) zero days
B) one or two days
C) three or four days
D) five or six days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents