Multiple Choice

Table 7.6
-Using Table 7.6, suppose activity I is delayed, taking eight days to complete instead of two days. Assume all other activity times remain the same. How much longer will the total project earliest completion time become?
A) zero days
B) one or two days
C) three or four days
D) five or six days
Correct Answer:
Verified