The following table contains a list of activities, with early- and late-start and finish times and crash costs for the network shown in the figure. All start and finish times and crash costs are on a per-week basis. Each activity can be reduced by one week at the most.
a. Determine the uncrashed activity lengths for activities A though K.
b. Determine the minimum completion cost for this project if each week carries a fixed cost of $1,000.