Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, what is the critical path and expected completion time for this project?
A) D-E; 29.5 weeks
B) A-B-C; 25 weeks
C) D-E; 27.5 weeks
D) A-B-C; 26.5 weeks
Correct Answer:
Verified