Table 7.14 You Are Responsible for Managing a Project with the Following

Question 114

Multiple Choice
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks).
 
-Using Table 7.14, what is the critical path and expected completion time for this project?
A) D-E; 29.5 weeks 
B) A-B-C; 25 weeks 
C) D-E; 27.5 weeks 
D) A-B-C; 26.5 weeks

Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
Table 7.14 You are responsible for managing a project with the following activities (times are given in weeks) .    -Using Table 7.14, what is the critical path and expected completion time for this project? A)  D-E; 29.5 weeks B)  A-B-C; 25 weeks C)  D-E; 27.5 weeks D)  A-B-C; 26.5 weeks
-Using Table 7.14, what is the critical path and expected completion time for this project?


A) D-E; 29.5 weeks
B) A-B-C; 25 weeks
C) D-E; 27.5 weeks
D) A-B-C; 26.5 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents