Table 7.13 All Activity Times for the Project Are in Weeks

Question 110

Multiple Choice
Table 7.13
All activity times for the project are in weeks.
 
-Using Table 7.13, if the expected time for activity H is changed to 25 weeks, by how many weeks will the project's expected completion time increase?
A) It will increase by one week. 
B) It will increase by three weeks. 
C) It will increase by two weeks. 
D) It will increase by four weeks.

Table 7.13
All activity times for the project are in weeks.
Table 7.13 All activity times for the project are in weeks.    -Using Table 7.13, if the expected time for activity H is changed to 25 weeks, by how many weeks will the project's expected completion time increase? A)  It will increase by one week. B)  It will increase by three weeks. C)  It will increase by two weeks. D)  It will increase by four weeks.
-Using Table 7.13, if the expected time for activity H is changed to 25 weeks, by how many weeks will the project's expected completion time increase?


A) It will increase by one week.
B) It will increase by three weeks.
C) It will increase by two weeks.
D) It will increase by four weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents