To calculate the probability of completing a project by a certain date:
A) the expected completion time of the project is taken to be the sum of the activity times on the shortest path.
B) the variance of the distribution of project completion times is taken to be one-sixth the difference between the latest finish time and the earliest finish time of the last activity in the project.
C) we assume that the activity durations are independent of each other so that the normal distribution can be used.
D) we need only the parameters of the beta distribution for the finish node of the diagram.

To calculate the probability of completing a project by a certain date:


A) the expected completion time of the project is taken to be the sum of the activity times on the shortest path.
B) the variance of the distribution of project completion times is taken to be one-sixth the difference between the latest finish time and the earliest finish time of the last activity in the project.
C) we assume that the activity durations are independent of each other so that the normal distribution can be used.
D) we need only the parameters of the beta distribution for the finish node of the diagram.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents