Question 106

Multiple Choice
Table 7.2
 
-Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase?
A) fewer than or equal to 2 weeks 
B) greater than 2 weeks but fewer than or equal to 4 weeks 
C) greater than 4 weeks but fewer than or equal to 6 weeks 
D) greater than 6 weeks

Table 7.2
Table 7.2    -Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase? A)  fewer than or equal to 2 weeks B)  greater than 2 weeks but fewer than or equal to 4 weeks C)  greater than 4 weeks but fewer than or equal to 6 weeks D)  greater than 6 weeks
-Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase?


A) fewer than or equal to 2 weeks
B) greater than 2 weeks but fewer than or equal to 4 weeks
C) greater than 4 weeks but fewer than or equal to 6 weeks
D) greater than 6 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents