Multiple Choice

Table 7.2
-Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase?
A) fewer than or equal to 2 weeks
B) greater than 2 weeks but fewer than or equal to 4 weeks
C) greater than 4 weeks but fewer than or equal to 6 weeks
D) greater than 6 weeks
Correct Answer:
Verified
Related Questions
Q101: Table 7.14
You are responsible for managing a
Q102: When using the beta distribution for estimating