Use the information in the preceding table and sequence the seven jobs using first come, first served (FCFS) and earliest due date (EDD). Calculate the average flow time and average past due. It is now time 5.
Correct Answer:
Verified
The FCFS sequence is:
Avera...
Avera...
View Answer