In assembly-line balancing, cycle time (the ratio of available production time to scheduled production) is the:
A) minimum time that a product is allowed at each workstation.
B) maximum time that a product is allowed at each workstation.
C) inverse of the minimum number of workstations needed.
D) sum of all the task times divided by the maximum number of workstations.
E) equivalent of the maximum task time among all tasks.
Correct Answer:
Verified
Q287: A product-oriented layout would be MOST appropriate
Q288: Cycle time is computed as:
A) desired output
Q289: Which of the following is TRUE regarding
Q290: In assembly-line balancing, the theoretical minimum number
Q291: Four hundred and eighty minutes of production
Q293: Four hundred and eighty minutes of production
Q294: The central problem in product-oriented layout planning
Q295: The assumptions necessary for a successful product-oriented
Q296: Which of the following is NOT a
Q297: A production line is to be designed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents