A network consists of the activities in the following list. Times are given in weeks.
(a) Draw the network diagram.
(b) Calculate the ES, EF, LS, LF, and Slack for each activity.
(c) What is project completion time?
Correct Answer:
Verified
Q73: Define slack time.
Q74: What is the objective of critical path
Q75: Draw the AOA and AON networks for
Q76: In PERT analysis, the identification of the
Q77: A network consists of the following list.
Q79: Which of the following statements concerning CPM
Q80: The PERT pessimistic time estimate is an
Q81: The beta distribution is used in project
Q82: The expected activity time in PERT analysis
Q83: Analysis of a PERT problem shows the